Flooring · 7 steps
Polyaspartic & flake floors
Follow the solid-color or flake route, then seal and cure the surface.
Step 1. Prepare and check the site
Test moisture, remove contamination, repair defects and create the required profile. Measure air, slab and material conditions, including dew point. Fast cure does not replace proper preparation.
- Air and humidity
- Slab and dew point
- Material temperature
Check dew-point margin and every product limit, not just air temperature. Step 2. Apply the approved primer
Use the system-approved primer and inspect its sealing and overcoat condition. Apply polyaspartic directly to concrete only when that exact product permits it. An epoxy primer under polyaspartic makes a hybrid system.
Wear coatBody coatPrimerConcreteFollow the approved layer sequence. Thicknesses are schematic. Step 3. Measure and mix
Follow the product ratio and measurement basis; polyaspartics are not universally 1:1. Use only approved colorants and keep tools and decorative media dry. Size batches for the actual working time, including mixing, transport and finishing.
Measure A + BMix thoroughlyFollow the product ratio and measurement basis. No universal ratio is shown. Step 4. For a solid-color floor
Apply the approved pigmented layer at its specified coverage. Work in controlled bands, keep a live edge and finish promptly. Confirm opacity and any additional wear-coat requirement. Skip the flake step if this is your chosen finish.
- Coated area
- Wet edge
Maintain a wet edge and check the specified build. Step 5. For a flake floor
Broadcast approved dry flakes into the receptive binder to the specified coverage. After sufficient cure, remove protrusions and vacuum loose media. A light sprinkle and a full broadcast are different designs, not interchangeable quantities.
Remove loose flakes after sufficient cure, then apply the specified seal coat. Step 6. Seal the surface
Apply the specified seal/wear coats within the recoat window. Textured broadcast floors may need more material than smooth surfaces. Leave no sharp flakes or loose media, and retain the texture required for the intended use.
Wear coatBody coatPrimerConcreteFollow the approved layer sequence. Thicknesses are schematic. Step 7. Protect until ready for use
Track coat times and follow the actual service-cure schedule. Walking readiness does not establish vehicle or chemical readiness. Do not promise a one-day installation without checking the whole assembly and site conditions.
RecoatWalkingVehicle trafficWater & chemicalsUse the actual product release requirements, not one shared countdown.